E-Rate Application Timeline & Process

E-Rate Application Process Timeline – Dates to Remember for E-Rate Year

 

Click here to download a printer friendly PDF of the table below – Download E-Rate Application Timeline & Process Chart

FOCUS E-RATE APPLICATION PROCESS RECURRING E-RATE SERVICES NON-RECURRING E-RATE SERVICES
APPLICABLE FORM File Form 470 (Step 4) File Form 471 (Step 6) File Form 486 (Step 8) File Form 472 BEAR Form or Setup Accounts for SPI (Step 9) File Form 472 BEAR Form or Setup Accounts for SPI (Step 9)
TASK Work to identify E-Rate priorities for the funding year Competitive bidding, school review of bids & selection of E-Rate service providers E-Rate application window to request discounts E-Rate review, begin E-Rate application approval process with USAC File Form 486 in a timely manner Delivery Dates (CAT 1 or CAT 2) Be aware of deadline to file Form 472 or work with providers to setup SPI Discounts Purchase/Install dates Be aware of deadline to file Form 472 or work with providers to setup SPI Discounts
TIMELINE/DEADLINE Sept – Dec Oct – Jan Jan – Mar Mar – June 120 days from FCDL or Service start date (whichever is later) Funding Year: July 1 to June 30 Oct 28 of following year Funding Year: April 1 – Sept 30 Funding Year: Jan 28 (of following year)